Project: Portland Airport Deicing system project. 30" HDPE outfall into the Columbia River
Product: 1100 ft. of SDR 9 30" HDPE pipe
General Contractor: Northwest Underwater Construction
Soil Conditions: Soft Clay & Sand
Project challanges: High Winds at exit barge locations on river / Preventing drilling fluid frac out in soft soil conditions / Minimizing the drilling fluid / cuttings into the Columbia River.
Lifting drill head in 50ft. of water with crane barge
After tooling change Lower 34" reamer down for preream
Project: Rainier Effluent Outfall Project / Bore from Rainier Treatment Plant to the Defuser location 150 ft. off shore in 45ft. of water
General Contractor: Stellar J Corporation
Product: 750ft. 24" HDPE PIPE Conditions: Sand / silty sand
After pulling the pipe & the reamer back to the exit point in the river, the pipe would still not pull back easy. Divers went down to inspect and found the Reamer and first two drill rods wrapped in 1 1/2" cable. The divers cut the cable to free the Reamer & pipe
We think the cable was from on old existing Mill site or an ancor cable from past dredging operations in the area.
On the secound pull back, the divers inspected the pipe and reamer for more cable before it entered the ground.
Setup in Industrial area / Drilling Pilot
Driving 120 ft. of 30" casing though surface cobble / gravels
Project: Install 24" casing for an 18" gas main installation crossing Interstate 80 & the Rail Road Tracks
General Contractor: Silver State Boring / Gardenerville, NV / Rick Landino
Conditions: Surface 20' was gravels with cobble / Cemented hardpan with gravels and cobbles below
Project: Lake Francis, Montana - water intake system
Product: 2800 ft. Bore of 28'' OD HDPE Exiting 1500 ft. off shore, 35 ft. Deep in Lake Bottom
Conditions: 20ft. of surface clay to sand stone out to lake bottom
Project: Ojia, CA - siphon sewer lines under San Antonio Creek
Product: 1600 ft. of 16'' and 24'' HDPE pipes and structures Conditions: Top 25ft. of Large Cobble to Clay Stone / Rock
Project: 2008 Puget Sound Engery / Bellevue Lake Hills & Black Diamond HP Lateral HDD Projects
General Contractor: Alaska Continental Pipeline / Rockford Corporation
Product: 16" Steel Coated Gas Pipeline / 1900, 1100, & 800 ft. HDD Bores
Conditions: Lake Hills, Bellevue, WA 800 ft. HDD project under Kelsy Creek: 10ft. of road base Glacial Till, then 15 ft. of Peat bog
material, and finally dense cemented glacial till to 60ft. The Black Diamond HDD Projects in Kent, WA : 1100 ft. Bore under
Hwy 167 & the 1900ft. Green River Bore were Mostly Clay with some gravel lenses
Project: Gas Pipeline project for HC Price Co. near Ninilchick Alaska
Product: 12" Steel Gas Pipeline / 8 HDD River Crossings up to 2000 ft. in length
Conditions: Mixed Soil conditions, Silty Sands, clay, gravels, & coal layers
Pipe Ramming & Cleaning 2ea. 200ft. runs of 36" HDD Conductor Casings driven though the cobble layer
First Pilot Exits on Target
Project: City of Redding, CA Pressure Sewer Project / Twin HDPE pipes crossing the Sacramento River
Product: 2ea. 1600 ft. 16" HDPE Pipes
Conditions: 20 ft. of 12" minus sized surface cobble on both sides, changing to Siltstone Rock at greater depths under the River
Project: Umpqua Basin Water Association (UBWA) / Water Main Replacement / North Umpqua River HDD / Roseburg, Oregon
Product: 950ft. 22" HDPE pipe
Conditions: Fractured to Solid Sand Stone / Silt Stone ( Medium Density Rock )